Projects
COMPLETED & ACTIVE PROJECTS
2018 - PRESENT - project Manager (Emery Sapp & Sons, Inc.)
Project Size Note for Private Contracts: Small: < $1M / Medium: $1M - $5M / Large: > $5M
COMPLETED / ACTIVE PROJECTS
Project Name and Location: Hwy 86 Rd Widening, Bridge & Entry Rd - Ridgedale, MO
Completion: Active (Est. Completion Winter 2023)
Market: Private/Partially State Funded (Big Cedar, LLC)
Role: (PM) General Contractor
Project Size: Large
Approx. Project Duration: 6 Months
Scope of Work: Widening of Existing State Road / New Bridge and Roadway
Clearing and Demo of Existing Improvements
Installation of Underground Utilities
Earthwork and Site Grading
Construction of New Bridge, Roadway, and Pedestrian Pathway
Roadway Signals and Lighting Improvements
Bridge Construction with Soil Nail Retaining Walls
MSE Retaining Walls
Project Name and Location: Silver Dollar City Parkway - Branson, MO
Completion: Active (Est. Completion Winter 2023)
Market: Private (Silver Dollar City Attractions)
Role: (PM) General Contractor
Project Size: Large
Approx. Project Duration: 10 Months
Scope of Work: Roadway and Parking Lot Improvements
Clearing and Demo of Existing Improvements
Installation of Storm Drainage Utilities
Site Grading and Paving
Construction Bridge, Pedestrian Underpass and Retaining Walls.
Project Name and Location: 32nd Street Widening - Joplin, MO
Completion: Active (Est. Completion Winter 2023)
Market: Public (City of Joplin, MO)
Role: (PM) General Contractor
Project Size: $8M+
Approx. Project Duration: 18 Months
Scope of Work: Road Widening and Improvements
Clearing and Demo of Existing Improvements
Installation of Underground Utilities
Site Grading and Landscaping
Construction of New Roadway and Pedestrian Pathways
Project Name and Location: MoDOT 221021-G01 - Carterville, MO
Completion: Summer 2023
Market: Public (Missouri Department of Transportation)
Role: (PM) General Contractor
Project Size: $1.8M+
Approx. Project Duration: 4 Months
Scope of Work: Roadway Improvements
Highway Slide Repairs and Storm Drainage Improvements.
Project Name and Location: SDC Dorms - Branson, MO
Completion: Active Project (Est. Completion Fall 2023)
Market: Private
Role: (PM) Subcontractor
Project Size: Small
Approx. Project Duration: 8 Months
Scope of Work: Site Work
Site Clearing, Grading and Paving
Installation of Underground Utilities: Storm Drainage/Water Line/Sanitary Sewer
Project Name and Location: Golf Quarters (Fall Creek Townhomes Phase 2) - Branson, MO
Completion: Active Project (Est. Completion Fall 2023)
Market: Private
Role: (PM) Subcontractor
Project Size: Small
Approx. Project Duration: 10 Months
Scope of Work: Site Work
Site Clearing Grading and Paving
Installation of Underground Utilities: Storm Drainage/Water Line/Sanitary Sewer
Project Name and Location: Buc-ee's - Springfield, MO
Completion: Active Project (Est. Completion Winter 2023)
Market: Private
Role: (Assist. PM) Subcontractor
Project Size: Large
Approx. Project Duration: 18 Months
Scope of Work: Site Work
Clearing and Demo of Existing Improvements
Installation of Underground Utilities: Storm, Water, Gas, Sanitary Sewer, Electric.
Site Grading and Paving
Project Name and Location: Frisco Senior Village Phase 2 - Bolivar, MO
Completion: Spring 2023
Market: Private
Role: (PM) Subcontractor
Project Size: Medium
Approx. Project Duration: 1 Year
Scope of Work: Site Work
Clearing
Grading
Storm / Water / Sanitary Sewer Improvements
Site Paving
Project Name and Location: Springfield Sports Complex - Springfield, MO
Completion: Winter 2022
Market: Private
Role: (PM) Site Subcontractor
Project Size: Medium
Approx. Project Duration: 18 Months
Scope of Work:
Site Grading
Installation of Underground Utilities
Storm Drainage
Sanitary Sewer
Water Main
Gas
Site Paving: Roadway and Pedestrian Pathways
Project Name and Location: Garrett Road Widening and Mt. Hebron Park - Rogers, AR
Completion: Summer 2023
Market: Public (City of Rogers, AR)
Role: General Contractor
Project Size: $10M+
Approx. Project Duration: 2 Years
Scope of Work:
Site Grading, Paving and Landscaping
Underground Utilities: Storm, Sewer, Water
Building Construction: Subcontracted Out
Project Video: https://youtu.be/gofgu1cmtMI
Project Name and Location: Fall Creek Townhomes - Branson, MO
Completion: Spring 2023
Market: Private
Role: Subcontractor
Project Size: Medium
Approx. Project Duration: 15 Months
Scope of Work: Site Work
Site Grading and Paving
Installation of Underground Utilities: Storm Drainage/Water Line/Sanitary Sewer/Electric.
Project Name and Location: Wilderness Mountain - Kimberling City, MO
Completion: Summer 2022
Market: Private
Role: Subcontractor
Project Size: Medium
Approx. Project Duration: 8 Months
Scope of Work: Site Grading
Project Name and Location: MoDOT Route 14 Widening - Ozark, MO
Completion: Winter 2022
Market: Public (MoDOT)
Role: General Contractor
Project Size: $9M+
Approx. Project Duration: 18 Months
Scope of Work:
Road Widening and Improvements
Grading
Storm Drainage Improvements
Installation of Pedestrian Underpass and MSE Wall
Roadway Concrete and Asphalt Paving
Project Website: https://www.modot.org/jackson-street-route-14-widening-completed
Project Pictures: Click Here
Project Name and Location: MoDOT BUS 65 ADA Improvements - Hollister, MO
Completion: Winter 2022
Market: Public (MoDOT)
Role: General Contractor
Project Size: +/- $1M
Approx. Project Duration: 3 Months
Scope of Work: New Sidewalk Construction and Traffic Signal Improvements
Project Name and Location: MSSU Residence Facility, Site Paving - Joplin, MO
Completion: 2021
Market: Private
Role: Subcontractor
Project Size: Small
Approx. Project Duration: 1 Month
Scope of Work: Site Concrete for New Residence Facility
Project Name and Location: Freeman Hospital Parking Lot Extension - Joplin, MO
Completion: 2021
Market: Private
Role: General Contractor
Project Size: Small
Approx. Project Duration: 4 Months
Scope of Work: Hospital Parking Lot Extension
Project Name and Location: Corwin Dealership - Springfield, MO
Completion: 2021
Market: Private (City of Springfield, MO)
Role: Subcontractor
Project Size: Small
Approx. Project Duration: 6 Months
Scope of Work: Concrete Site Paving
Project Name and Location: Surface Project 4011- Joplin, MO
Completion: 2020
Market: Public (City of Joplin, MO)
Role: General Contractor
Project Size: $60k +
Approx. Project Duration: 1 Month
Scope of Work: Sidewalk and Street Improvements
Project Name and Location: MoDOT Route D Widening and Improvements - Bolivar, MO
Completion: 2020
Market: Public (City of Bolivar, MO / MoDOT)
Role: General Contractor
Project Size: $300k +
Approx. Project Duration: 2 Months
Scope of Work: Construction of New Turn Lane for Existing Hwy and Storm Drainage Improvements
Project Name and Location: Nixa Fire Station New Training Facility, Site Paving - Nixa, MO
Completion: 2020
Market: Public (City of Nixa, MO)
Role: General Contractor
Project Size: Small
Approx. Project Duration: 1 Month
Scope of Work: Site work, and Construction of Concrete Pad for New Training Facility
Project Name and Location: SGF Airport Parking Lot Extension - Springfield, MO
Completion: 2020
Market: Public (City of Springfield, MO)
Role: General Contractor
Project Size: $2M +
Approx. Project Duration: 8 Months
Scope of Work: Airport Parking Lot Extension
Grading
Storm Drainage Improvements
Concrete / Asphalt Paving
Project Name and Location: Silverback Landing Subdivision - Pittsburg, KS
Completion: 2020
Market: Private
Role: General Contractor
Project Size: Medium
Approx. Project Duration: 1 Year
Scope of Work: Site Development for new Subdivision Lots
Clearing
Grading
Storm Drainage
Sanitary Sewer Improvements
Water Line Improvements
Site Paving
Project Name and Location: Rogers Heritage High School Baseball/Softball Complex - Rogers, AR
Completion: 2020
Market: Public (City of Rogers, AR)
Role: Subcontractor
Project Size: $1.4M +
Approx. Project Duration: 6 Months
Scope of Work: Site Work
Earthwork
Storm Drainage Improvements
Sanitary Sewer Improvements
Water Line Improvements
Project Name and Location: Springfield-Branson Airport Apron Extension - Springfield, MO
Completion: 2019
Market: Public (City of Springfield, MO)
Role: General Contractor
Project Size: +/- $1M
Approx. Project Duration: 2 Months
Scope of Work: SGF Airport Apron Extension
Project Name and Location: Koinonia Christian Campus Residential Improvements - Joplin, MO
Completion: 2019
Market: Private
Role: General Contractor
Project Size: Small
Approx. Project Duration: 2 Months
Scope of Work: Grading, Storm Drainage Improvements, Site Paving
Project Name and Location: Hy-Vee Superstore - Springfield, MO
Completion: 2019
Market: Private
Role: General Contractor
Project Size: Small
Approx. Project Duration: 1 Month
Scope of Work: Site Clearing for New Hy-Vee Facility
Project Name and Location: Missouri American Water - Water Line Improvements @ 24th St. & Highview Ave. - Joplin, MO
Completion: 2019
Market: Private
Role: General Contractor
Project Size: Small
Approx. Project Duration: 1 Month
Scope of Work: Water Line Improvements
Project Name and Location: Missouri American Water - Water Line Improvements @ 20th St. & Indiana Ave. - Joplin, MO
Completion: 2019
Market: Private
Role: General Contractor
Project Size: Small
Approx. Project Duration: 1 Month
Scope of Work: Water Line Improvements
Project Name and Location: Frisco Senior Village Phase 1 - Bolivar, MO
Completion: 2019
Market: Private
Role: Subcontractor
Project Size: Medium
Approx. Project Duration: 1 Year
Scope of Work: Site Work
Clearing
Grading
Storm / Water / Sanitary Sewer Improvements
Site Paving
Project Name and Location: Surface Project 4008- Joplin, MO
Completion: 2019
Market: Public (City of Joplin, MO)
Role: General Contractor
Project Size: $3.5M +
Approx. Project Duration: 1 Year
Scope of Work: Sidewalk and Street Improvements
Project Name and Location: Silverback Way - Pittsburg, KS
Completion: 2018
Market: Public (City of Pittsburg, KS)
Role: General Contractor
Project Size: +/- $1.2M
Approx. Project Duration: 8 Months
Scope of Work: New Roadway Construction, Storm Drainage and Water Line Improvements
Project Name and Location: SAIA Trucking Facility - Strafford, MO
Completion: 2018
Market: Private
Role: Subcontractor
Project Size: Small
Approx. Project Duration: 6 Months
Scope of Work: Site Grading, and Paving, Storm Drainage, Water, and Sanitary Sewer Line Improvements)
2017 - assistant project Manager (Emery Sapp & Sons, Inc.)
PROJECTS
Project Name and Location: Interstate 44 Acceleration/Deceleration Ramps Extensions - Springfield, MO
Year Completed: 2017
Market: Public (MoDOT)
Role: General Contractor
Scope of Work: Roadway Improvements
Project Name and Location: Route MM Pavement Repairs - Springfield, MO
Year Completed: 2017
Market: Public (MoDOT)
Role: General Contractor
Scope of Work: Roadway Improvements
Project Name and Location: Mercy Bolivar Clinic - Bolivar, MO
Year Completed: 2017
Market: Private
Role: Site Work Subcontractor
Scope of Work: Site Grading, Paving, and Storm Drainage Improvements
Project Name and Location: 32nd Street and Central City Road Roundabout - Joplin, MO
Year Completed: 2017
Market: Public
Role: General Contractor
Scope of Work:
Site Grading
Storm Drainage Improvements
New Roadway Construction and Landscaping
Project Name and Location: Primatara Residential Development - Springfield, MO
Year Completed: 2022
Market: Private
Role: Subcontractor
Scope of Work: Site Grading, Paving, and Storm Drainage Improvements
Project Name and Location: ADA Improvements on MoDOT Rte 66 - Joplin, MO
Year Completed: 2017
Market: Public
Role: General Contractor
Scope of Work: Sidewalk Improvements
Project Name and Location: City of Joplin Surface Project 4003 - Joplin, MO
Year Completed: 2017
Market: Public (City of Joplin)
Role: General Contractor
Scope of Work: Street and Sidewalk Improvements
2014 - 2016 Project Manager Intern (Emery Sapp & Sons, Inc.)
PROJECTS
MoDOT Hwy 65 Road Widening, Bride Reconstruction, and Replacement - Springfield, MO
Rogers Municipal Airport Runway Reconstruction - Rogers, AR
Mercy Pittsburg Clinic Grading and Sitework - Pittsburg, KS
St. Louis Avenue Widening - Joplin, MO
Pleasant Gove Road Improvements - Rogers, AR
MoDOT Hwy 60 Overpass and Road Widening - Rogersville, MO
XNA Regional Airport East Apron Expansion - Bentonville, AR
Pleasant Gove Road Improvements - Rogers, AR
Rogers Municipal Airport Concrete Apron Expansion - Rogers, AR
JTEC Rail Loop - Springfield, MO
JTEC Pond Cleanout - Springfield, MO
Interstate 44 Overpass - Joplin, MO
Top of the Rock Roundabout and Road Improvements - Hollister, MO
New Mercy Hospital - Joplin, MO
Northpark Mall Parking Lot Improvements - Joplin, MO
Walmart Neighborhood Market - Springfield, MO
Rogers Municipal Airport Concrete Apron Improvements - Rogers, AR
Branson West Municipal Airport New Apron Construction - Branson West, MO